2022-07-07 SID 615 Minutes CERTIFICATE
The undersigned hereby certify that they are the Chairperson and Clerk of Sanitary and Improvement District
Number 615 of Douglas County,Nebraska,(the"District")and hereby further certify as follows:
1. Annexed to this certificate is a true and correct transcript of the proceedings of the Board of Trustees of the
District relating to a meeting of said District held on the date and at the time reflected in the meeting minutes contained
in said foregoing transcript(the"Meeting"). All of the proceedings of the District and of the Board of Trustees thereof
which are set out in the annexed and foregoing transcript have been fully recorded in the journal of proceedings of the
District and the undersigned District Clerk has carefully compared the annexed and foregoing transcript with said journal
and with the records and files of the District which are in such Clerk's official custody and said transcript is a full,true
and complete copy of said journal,records and files which are set out therein.
2. Advanced notice for the Meeting was given by publication as set forth in the affidavit of publication
contained in the foregoing transcript and was mailed to the Clerk of the municipality or county within whose zoning
jurisdiction the District is located at least seven days prior to the date of the Meeting. Advanced notice for the Meeting,
including notice of agenda subjects, was given to all members of the Board of Trustees. All news media requesting
notification of meetings of said body were provided with advanced notice of the times and places of such meetings and
the subjects to be discussed.
3. All of the subjects addressed at the Meeting were contained in the agenda for the Meeting, which agenda
was kept continually current and readily available for public inspection at the address listed in the meeting notice for the
Meeting and a copy of which is attached to this Certificate; such subjects were contained in said agenda for at least 24
hours prior to the Meeting and each agenda item was sufficiently descriptive to give the public reasonable notice of the
matters to be considered at the Meeting.
4. A current copy of the Nebraska Open Meetings Act was available and accessible to members of the public,
posted during the Meeting in the room in which such Meeting was held and all in attendance at the Meeting were
informed that such copy of the Nebraska Open Meetings Act was available for review and were informed of the location
of such copy in the room in which such Meeting was being held. At least one copy of all resolutions and other
reproducible written materials,for which actions are shown in said proceedings,was made available for examination and
copying by members of the public at the Meeting.
5. The minutes of the Meeting were in written form and available for public inspection within ten(10)working
days after the Meeting or prior to the next convened meeting, whichever occurred earlier, at the office of the District;
within thirty(30)days after the date of the Meeting, a copy of the minutes of the Meeting was sent to the Clerk of the
municipality or county within whose zoning jurisdiction the District is located.
6. No litigation is now pending or threatened to restrain or enjoin the District from the issuance and delivery of
any warrants or other obligations issued by the District or the levy and collection of tax or other revenues or relating to
any of the improvements for which any such warrants or other obligations were or are issued nor in any manner
questioning the proceedings and authority under which any such warrants or other obligations were or are issued or
affecting the validity thereof; neither the corporate existence or boundaries of the District nor the title of its present
officers to their respective offices is being contested; no authority or proceedings for the issuance of any warrants or
other obligations by the District have been repealed,revoked or rescinded as of the date hereof. All actions taken by the
Board of Trustees referred to in said transcript were taken at a public meeting while open to the attendance of the public.
IN WITNESS WHEREOF,we have hereunto affixed our official signatures this 7th day of July,2022.
S
C-#.
David Lanoha,Chairman
CassiateY,Clerk
MINUTES OF THE MEETING OF THE BOARD OF TRUSTEES OF
SANITARY AND IMPROVEMENT DISTRICT NO. 615 OF DOUGLAS
COUNTY,NEBRASKA HELD AT 4:30 P.M. ON JULY 7, 2022
The meeting of the Board of Trustees of Sanitary and Improvement District No. 615 of
Douglas County, Nebraska was convened in a public session at 4:30 p.m. on July 7, 2022 at
17070 Wright Plaza, Ste. 200, Omaha,Nebraska, 68130 and pursuant to the terms and conditions
set forth in the Nebraska Open Meetings Act, a copy of which was made available for review to
all in attendance at these proceedings, in accordance with State Law.
Trustees David Lanoha, Chris Lanoha, and Cassie Preister were present at the meeting.
Trustee Jason Lanoha was absent.
Notice of the meeting was given in advance thereof by publication in The Daily Record
on June 22 and 29, 2022, a copy of the Proof of Publication being attached to these minutes.
Notice of the meeting was simultaneously given to all members of the Board of Trustees and a
copy of their Acknowledgement of Receipt of Notice is attached to these minutes. Availability
of the agenda was communicated in the published notice and in the notice of the Trustees of this
meeting. All proceedings of the Board were taken while the convened meeting was open to the
attendance of the public.
The Clerk then certified that notice of this meeting had been given to the City of Omaha,
Nebraska and the Douglas County Clerk at least seven days prior to the time set by the Board of
Trustees for this meeting and filed his Certificate to that effect, said Certificate being attached to
these minutes and made part hereof by this reference.
First, the Chairman presented proof of publication in connection with the Resolution of
Necessity recommending that the District enter into a Water Main Extension Agreement with
Metropolitan Utilities District, for and in consideration of the construction of the water main
extension and any related appurtenances,together with an estimate of the total cost relating to the
project,the same having been published on June 22 and 29, 2022 in The Daily Record, a paper of
general circulation in Douglas County, Nebraska. It was then noted that no one from the public
appeared in opposition of the above resolution and the same had been published in three (3)
conspicuous places within the boundaries of the District.
After discussion, the Resolution contained in Exhibit "A" attached hereto and by this
reference incorporated herein was duly introduced, seconded and upon a roll call vote of"aye"
by the Trustees, was unanimously adopted; the Trustees then passed the following resolutions:
BE IT RESOLVED by the Board of Trustees of Sanitary and
Improvement District No. 615 of Douglas County, Nebraska that
the Resolution of Advisability and Necessity for the District to
enter into a Water Main Extension Agreement with Metropolitan
Utilities District ("MUD"), for construction of the water main
extension and any related appurtenances, and the payment of any
costs related thereto, be and hereby is approved, the same having
been preliminarily approved, in form, at the June 9, 2022 meeting
of the District.
BE IT FURTHER RESOLVED that the Board of Trustees
further authorize the payment of$1,205,281.00 be made to MUD
from the Construction Fund Account of the District as part of these
proceedings and in accordance with the approval of the above
resolution.
The Chair then presented the following statements for payment from the Construction
Fund Account of the District and the Clerk was directed to attach a copy of said statements to
these minutes:
a. TAB Construction Co. for completion of a portion of the Sanitary $361,211.72
and Storm Sewer—Section 1 & 2 Improvements and in accordance
with Pay Est.No. 6.
b. MBC Construction, LLC for completion of a portion of the Paving $740,571.99
Section I improvements in accordance with Pay Est.No. 1.
c. Metropolitan Utilities District for construction of the water main $1,205,281.00
extension and related appurtenances and payment of pioneer main
fees pursuant to the above-approved Water Main Ext. Agreement.
d. Fullenkamp Jobeun Johnson& Beller, LLP for legal services ren- $79,194.81
dered in connection with items a.), b.) 5% and c.) (2%) hereinabove.
e. D.A. Davidson& Co. for underwriting services relating to Construe- $47,725.19
tion Fund Warrants issued at this meeting (2%).
Then, upon a motion duly made, seconded and upon a roll call vote of "aye" by the
Trustees David Lanoha, Chris Lanoha, and Cassie Preister, the following Resolutions were
unanimously adopted:
BE IT RESOLVED by the Board of Trustees of Sanitary and
Improvement District No. 615 of Douglas County, Nebraska that the Chairman
and Clerk be and they hereby are authorized and directed to execute and deliver
Warrant Nos. 149 through 273, inclusive, of the District, dated the date of this
meeting, to the following payees, for the following services and in the following
amounts, said warrants to draw interest at the rate of 6% per annum in the General
Fund and 7% per annum in the Construction Fund, said warrants to be payable
from the Construction Fund Account of the District (interest payable annually)
and to be redeemed no later than five (5) years of the date of July 7, 2027 (the
"Construction Fund Warrants"), subject to extension of said maturity date by
order of the District Court of Douglas County, Nebraska after notice is given as
required by law,to-wit:
a) Warrant Nos. 149 through 166 for $20,000.00 each and
Warrant No. 167 for $1,211.72, all made payable to TAB
Construction Co. for completion of a portion of the Sanitary
and Storm Sewer — Section 1 & 2 Improvements and in
accordance with Pay Est. No. 6. CF
b) Warrant Nos. 168 through 227 for $20,000.00 each and
Warrant No. 228 for $5,281.00, all made payable to
Metropolitan Utilities District for construction of the water
main extension and related appurtenances and payment of
pioneer main fees pursuant to the above-approved Water Main
Ext. Agreement. CF
c) Warrant Nos. 229 through 265 for $20,000.00 each and
Warrant No. 266 for $571.99, all made payable to MBC
Construction, LLC for completion of a portion of the Paving
Section I improvements in accordance with Pay Est.No. 1. CF
d) Warrant Nos. 267 through 269 for $20,000.00 each and
Warrant No. 270 for $19,194.81, all made payable to
Fullenkamp Jobeun Johnson & Beller, LLP for legal services
rendered in connection with items a) (5%), b) (2%), and c)
(5%)hereinabove. CF
e) Warrant Nos. 271 and 272 for $20,000.00 each and Warrant
No. 273 for $7,725.19, all made payable to D.A. Davidson &
Co. for underwriting services relating to Construction Fund
Warrants issued at this meeting. CF
BE IT FURTHER RESOLVED by the Board of Trustees of Sanitary and
Improvement District No. 615 of Douglas County, Nebraska, that the District
hereby finds and determines and covenants, warrants and agrees as follows in
connection with the issuance of the Construction Fund Warrants: (i) the
improvements being financed by the Construction Fund Warrants are for essential
governmental functions of the District and are designed to serve members of the
general public on an equal basis; (ii) all said improvements have from the time of
their first acquisition and construction been owned, are owned and are to be
owned by the District or another political subdivision; (iii) to the extent special
assessments have been or are to be levied for any of said improvements, such
special assessments have been or are to be levied under Nebraska law as a matter
of general application to all property specially benefited by said improvements in
the District; (iv) the development of the land in the District is for residential or
commercial use and the development of the land in the District for sale and
occupation by the general public has proceeded and is proceeding with reasonable
speed; (v) other than any incidental use of said improvements by a developer
during the initial period of development of said improvements, there have been,
are and will be no persons with rights to use such improvements other than as
members of the general public; (vi) none of the proceeds of said Construction
Fund Warrants have been or will be loaned to any private person or entity; and
(vii) and the District does not reasonably expect to sell or otherwise dispose of
said improvements, in whole or in part, prior to the last maturity of the
Construction Fund Warrants.
BE IT FURTHER RESOLVED by the Board of Trustees of Sanitary and
Improvement District No. 615 of Douglas County, Nebraska that the District
hereby covenants and agrees as follows in connection with the issuance of the
Construction Fund Warrants: (i) it will comply with all applicable provisions of
the Code, including Sections 103 and 141 through 150, necessary to maintain the
exclusion from gross income for federal income tax purposes of the interest on the
Construction Fund Warrants and (ii) it will not use or permit the use of any
proceeds of the Construction Fund Warrants or any other funds of the District nor
take or permit any other action, or fail to take any action, if any such action or
failure to take action would adversely affect the exclusion from gross income of
the interest on the Construction Fund Warrants. In addition, the District will
adopt such other resolutions and take such other actions as may be necessary to
comply with the Code and with all other applicable future laws, regulations,
published rulings and judicial decisions, in order to ensure that the interest on the
Construction Fund Warrants will remain excluded from federal gross income, to
the extent any such actions can be taken by the District.
The District covenants and agrees that (i) it will comply with all
requirements of Section 148 of the Code to the extent applicable to the
Construction Fund Warrants, (ii) it will use the proceeds of the Construction Fund
Warrants as soon as practicable and with all reasonable dispatch for the purposes
for which the Construction Fund Warrants are issued, and (iii) it will not invest or
directly or indirectly use or permit the use of any proceeds of the Construction
Fund Warrants or any other funds of the District in any manner, or take or omit to
take any action, that would cause the Construction Fund Warrants to be "arbitrage
bonds" within the meaning of Section 148(a) of the Code.
The District covenants and agrees that it will pay or provide for the
payment from time to time of all amounts required to be rebated to the United
States pursuant to Section 148(f) of the Code and any Regulations applicable to
the Construction Fund Warrants from time to time. This covenant shall survive
payment in full of the Construction Fund Warrants. The District specifically
covenants to pay or cause to be paid to the United States, the required amounts of
rebatable arbitrage at the times and in the amounts as determined by reference to
the Code and the Regulations. Pursuant to the "small issuer exception" set forth
below, the District does not believe the Construction Fund Warrants will be
subject to rebate.
The District covenants and agrees that (to the extent within its power or
direction) it will not use any portion of the proceeds of the Construction Fund
Warrants, including any investment income earned on such proceeds, directly or
indirectly, in a manner that would cause any Construction Fund Warrant to be a
"private activity bond".
The District makes the following representations in connection with the
exception for small governmental units from the arbitrage rebate requirements
under Section 148(f)(4)(D) of the Code:
(i) the District is a governmental unit under Nebraska
law with general taxing powers;
(ii) none of the Construction Fund Warrants is a private
activity bond as defined in Section 141 of the Code;
(iii) ninety-five percent or more of the net proceeds of
the Construction Fund Warrants are to be used for local
governmental activities of the District;
(iv) the aggregate face amount of all tax-exempt
obligations (other than "private activity bonds," but including any
tax-exempt lease-purchase agreements) to be issued by the District
during the current calendar year is not reasonably expected to
exceed$5,000,000; and
(v) the District (including all subordinate entities
thereof) will not issue in excess of $5,000,000 of tax-exempt
indebtedness (other than "private activity bonds" and certain
refunding bonds, but including any tax-exempt lease-purchase
agreements) during the current calendar year without first
obtaining an opinion of nationally recognized counsel in the area
of municipal finance that the excludability of the interest on the
Construction Fund Warrants from gross income for federal tax
purposes will not be adversely affected thereby.
BE IT FURTHER RESOLVED by the Board of Trustees of Sanitary and
Improvement District No. 615 of Douglas County, Nebraska that the District
hereby designates the Construction Fund Warrants as its "qualified tax-exempt
obligations"under Section 265(b)(3)(B)(i)(III) of the Code.
BE IT FURTHER RESOLVED by the Board of Trustees of Sanitary and
Improvement District No. 615 of Douglas County, Nebraska that this and the
preceding Resolutions are hereby adopted as the Certificate with Respect to
Arbitrage of the District pertaining to the Construction Fund Warrants and the
District hereby further certifies, as of the date of the registration of the
Construction Fund Warrants with Douglas County,Nebraska as follows:
1. The District reasonably anticipates that a portion of the
monies in its Bond Fund will be expended for payment of
principal of and interest on its bonds and/or construction
fund warrants of the District within 12 months after receipt
of such monies. The District hereby establishes a reserve
fund within its Bond Fund in connection with the issuance
of the Construction Fund Warrants in the amount equal to
the least of (i) 10% of the stated principal amount of the
Construction Fund Warrants, (ii) the maximum annual debt
service due on the Construction Fund Warrants during any
fiscal year, or (iii) 125% of the average annual debt service
for the Construction Fund Warrants over the term of such
warrants. That amount that is currently held in the
District's Bond Fund which exceeds the amount to be
expended for payment of principal and interest on the
bonds and/or construction fund warrants of the District
within 12 months after receipt of such monies, plus that
amount arrived at pursuant to the immediately preceding
sentence, will not be invested in any securities or any other
investment obligations which bear a yield, as computed in
accordance with the actuarial method, in excess of the yield
on the Construction Fund Warrants.
2. To the best of their knowledge, information, and belief, the
above expectations are reasonable.
3. The District has not been notified of any listing of it by the
Internal Revenue Service as an issuer that may not certify
its debt.
4. This Certificate is being passed, executed and delivered
pursuant to Section 1.148-2 (b) (2) of the Income Tax
Regulations under the Code (the "Regulations").
BE IT FURTHER RESOLVED by the Board of Trustees of Sanitary and
Improvement District No. 615 of Douglas County, Nebraska that the District
hereby authorizes and directs the Chair or Clerk to file or cause to be filed, when
due, an information reporting form pursuant to Section 149(e) of the Internal
Revenue Code of 1986, as amended (the "Code"), pertaining to the General Fund
Warrants and the Construction Fund Warrants; and,
No opinion of nationally recognized counsel in the area of municipal
finance has been delivered with respect to the treatment of interest on the General
Fund Warrants. Purchasers of the General Fund Warrants are advised to consult
their tax advisors as to the tax consequences of purchasing or holding the General
Fund Warrants.
[Remainder of page intentionally left blank]
MINUTES SIGNATURE PAGE FROM THE MEETING OF
SANITARY AND IMPROVEMENT DISTRICT NO. 615 OF
DOUGLAS COUNTY,NEBRASKA,HELD ON JULY 7,2022
There being no further business to come before the meeting, the meeting was adjourned.
Davi Lanoha, Chairman
Cassie Pr ,ester, Clerk
ACKNOWLEDGMENT OF
RECEIPT OF NOTICE OF MEETING
The undersigned Trustees of Sanitary and Improvement District No.615 of Douglas County,
Nebraska do hereby acknowledge receipt of advanced notice of a meeting of the Board of Trustees
of said District and that the agenda for such meeting, held at 4:30 p.m. on July 7, 2022, at 17070
Wright Plaza,Ste.200,Omaha,Nebraska and pursuant to the conditions set forth in Nebraska Open
Meetings Act,is kept continuously current and is available for review by the public at the office of
the District's counsel during normal business hours.
DATED this 7"'day of July, 2022.
CERTIFICATE
The undersigned being Clerk of Sanitary and Improvement District No. 615 of Douglas
County, Nebraska ("Sanctuary Ridge") hereby certifies that Notice of meeting of the Board of
Trustees of said District held on July 7,2022,was delivered to the City Clerk of Omaha,Nebraska,
via facsimile or electronic mail transmittal, at least seven(7)days prior to the date of said meeting.
The undersigned further certifies that the agenda for the meeting of the Board of Trustees of
said District was prepared and available for public inspection at the office of the District's counsel
contained in the notice of meeting given in advance thereof by publication in the Daily Record on
June 22 and 29, 2022, and that no items were added to the agenda after the commencement of the
meeting;and further,that the minutes for the meeting were available for public inspection within ten
(10)days of the date of said meeting and that a copy of the minutes of this meeting were sent to the
City of Omaha Clerk and the Douglas County Clerk,Omaha,Nebraska within thirty(30)days from
the date of this meeting.
C
Cassie
Preister, Clerk
FULLENKAMP JOBEUN THE DAILY 7�p RECORD
JOHNSON&BELLER LLP DA LL�1 RLj CORD
11440 West Center Road
Omaha,Nebraska 68144 OF OMAHA
SANITARY AND IMPROVEMENT
DISTRICT NO.615 OF JASON W.HUFF,Publisher
DOUGLAS COUNTY,NEBRASKA PROOF OF PUBLICATION
NOTICE OF MEETING
AND RESOLUTION
NOTICE IS HEREBY GIVEN that a meeting UNITED STATES OF AMERICA,
of the Board of Trustees of Sanitary and The State of Nebraska, J sa.
Improvement District No. 615 of Douglas District of Nebraska,
County,Nebraska will be held at 4:30 R.M.on
July 7,2022,at 17070 Wright Plaza,Ste. County of Douglas,
200,Omaha,Nebraska,which meeting will City of Omaha,
be open to the public and held in accordance
with the Nebraska Open Meetings Act. The
agenda for such meeting, kept continuously JASON W.HUFF and/or NI%LAUS STEWART
current, is available for public inspection at
11440 West Center Road, Omaha, Nebraska beingdulysworn,deposes and saythat they indudes the payment of bills of the District P are the
and the consideration and passing or amending
and passing the following Resolution,to-wit: PUBLISHER and/or LEGAL EDITOR
BE IT RESOLVED that the Board of of THE DAILY RECORD, of Omaha, a legal newspaper,printed and
Trustees
u a s Sanitary and Improvement District
No.615of Douglas County,Nebraskafind and published dailyin the Englishhmgaager having a bona fide paid
determine that it Is advisable and necessary circulation in Douglas County in excess of 300 copies, printed in
for the District Agreement enter into the Water Main Omaha,in said Countyof Douglas,for more than
Extension with MUD for the fifty-two weeks last
construction of a water main extension and past; that the printed notice hereto attached was published in THE
related equipment,pioneer main fees and other
appurtenances in Phase 1—Sanctuary Ridge, DAILY RECORD of on
which improvements shall be constructed in ?tule°r a'
accordance with the following agreement:
WATER MAIN EXTENSION AGREEMENT & 29, 2022
District Job No.100055001371
THIS AGREEMENT is entered into on July
2022,between the METROPOLITAN UTILITIES
DISTRICT OF OMAHA,NEBRASKA, ("District") That said Newspaper during that time wasss reegularlrlyy published and
and SID 615 id ofra Douglas County nt&payment
- • ps nl risvn•l +ir...;.,-t�-�� ofand Nebraska
In consideration of the unty("nt's payment
of One Million Two Hundred Five Thousand GENERAL NOTARY-State of Nebraska
Two Hundred Flahtv-One 00/100 Dollars 1111 NICOLE M.PALMER
($1 205.281.00 1 to the District, receipt of l ` My Comm. �g� p�r 1,20i$ in gt�en�and sworn to before
which is acknowledged,the District shall Install, S'ESOO�L yffi
as soon as is reasonably possible, Publisher's Fee $ me this day of
10' +1- of 16", 71130' +1- of 8" J e r I ' 2 q
and t 0'ar 1-of 6" ub water main in Additional Copies $345.22 I 1 '/f /
Sanctuary Ridge Subdivision at S. V(flb
229th St.&West Center Rd.to serve Total $
lots 1-97.
N •1. r mand for County,
as shown on the attached plat marked Exhibit State of Nebr
"A", together with such appurtenances, as
the District deems necessary (the "main"
or "mains"). This consideration includes
(1) the estimated total cost of the main
installation ($976.55400) and (2) the
estimated contributions to other pioneer mains
($228.727 00). The estimated total cost of
the main installation is$976.554 00 of which
cost the District shall assume$L,which is the
estimated difference in cost between a 16"8"
&6"main required and a 16"8"--&6" main -
• installed.
If the estimated total cost for the installation
of the main or the estimated contributions to
other pioneer mains,or both,are not sufficient
to cover the actual costs and/or contributions,
Applicant shall pay to the District the actual
costs and/or contributions,over the estimated
costs and/or contributions. The District may
refuse service from the main until such
payment(s)has/have been made.If the actual •
total cost for the installation of the main and
appurtenances or the estimated contributions •
to other pioneer mains,or both,are less than
the amount paid, the difference, of either or
both, whichever the case may be, shall be
refunded to the Applicant.
The District may permit others to tap the
main, but when an application to connect to _
the main is granted to serve the following real
property:
-The south 150'of the west 210'+/-of
the east 243+1-of the south 1/2 of the
southwest 1/4 of Section 26, T. 15 N.,
R.IO E.
abutting the main, the District shall collect If the main installation is delayed due to The Board of Trustees shall assess to the
the connection charge in accordance with the severe cold weather or when there is mare extent of special benefits, the cost of such
District's Water Rules and Regulations and than eight(8) inches of frost in the ground, improvements upon properties specially
procedures. The District shall refund.to the the District's Contractor shall not be requirao- benefitted thereby. All special assessments
Applicant the connection charges collected on to wort on the project without additional which may be levied upon the properties
an annual basis. The District shall not make compensation and/or an appropriate time ':. specially benefitted by such improvements shall,
extension. If frost is more than eight (8) when collected,be set aside and constitute a
refunds more than twenty(20)years after the
main extension agreement Is approved by the inches in depth,-the-additional compensation sinking fund for the payment of interest and
District. to install and/orthe appropriate time extension principal of said bonds. The District shall also
The District shall demand payment of will be negotiated between the District and cause to be levied annually a tax upon the
connection charges but shall not be obligated the Contractor and will be approved by the assessed value of all of the taxable property
to pursue litigation to collect a connection Applicant before proceeding. in the District except intangible property,which '
charge for refund purposes, but the District i The outer boundaries of the.area which together with said sinking fund derivedfrom
shall refuse individual connections to the water may become subject to special ascpcsments special assessments shall be sufidentto meet
for said improvements are proposed to be payment of the interest and main until the individual connection charge the same as the outer boundaries of Sanitary bonds as the same become due;said principal
shall is paid.The Applicant shall be regarded as a and Improvement District No.615 of Douglas be known as:the Sanitaryand Improvement
third party beneficiary under thls callecgreement County,Nebraska. District Tax and shall be ayable annually in
to pursue the Applicant's own colledtion of an Said agreement has been reviewed by Lamp money.
unpaid connection shallcha . Rynearson&Associates,Inc.,engineers for the
The Applicanttree not change the location District and said.engineers have filed with they property o petition ners rep ese tang.alma,signed
of
or grade of the shown)over which Applicant Clerk of the District,prior to the first publication footage
o owners which
may become a subjectbrity to
has control, as shown on Exhibit `A". The the assessment
for the cost
of es
Applicant shall grade the street(s)to conform to ofthis Resolution,an estimate of the total costs assessment for the cost of the improvements '
Exhibit"A`before the main installation.Where of said improvements,-including engineering as set forth herein,is filed with the Clerk of the
streets will not be payed, the right-of-way fees,legal fees,--fiscalfees,interest and other District within three(3)daysbefore the date of
("R.O.W.')shall be graded-to conform to the miscellaneous costs, which estimate Is In the the hearing on this Resolution,this Resolution
grade that has been legally established by the I sum of$1,500,000.00.: shall not be passed. - - -
appropriate governing body Wheresthe grade i To pay the cost of said Improvement the
has not been established;the grade-shall be Board. of Trustees shall have the power to SANITARY AND IMPROVEMENT DISTRICT
satisfactory-to.-the.District Where su:elaare to issue negotiable bonds of the District after NO.615 OF DOUGLAS COUNTY,NEBRASKA '
be paved,the District shall not begin the main such improvements have been completed and
Installation until the Applicant has completed accepted; said bonds to be called `'Sanitary - By:Dave Lanoha,Chairman
street paving,storm sewer Inlet installation and and Improvement District Bonds"and shall be Cassie Preister,Clerk
finish grading of.the R.O.W.If,within five(5) payable and bear interest as provided by the
years from date the main Installation is placed i Statutes of the State of Nebraska. 6/22,6/29 ZNEZ
in service,the District deems it nereccary to i The Board of Trustees shaltascocs to the
relocate,lower or raise the grade of all-or part 1 extent of special benefits, the cost of such
of the main as a:result of the Applicants failure j improvements upon properties specially
to have brought the street(s)=to grade before i benefitted thereby. All special assessments
the main Installation or a change in the grade t which may be levied upon the properties
or location of the street(s),then the Applicant? specially benefited by such improvements shall,
shall pay the District's costs of raising;lowering when collected,be set aside and constitute a
or relocating the main. sinking fund for the payment of interest and
The main shall be owned by and under principal of said bonds. The District shall also
the control of the District, its successors end , cause to be levied annually a tax upon the
assigns. assessed value of all of the taxable property
The District shall use reasonable efforts to 1 in the District except intangible property,which
avoid damaging or removing erosion control ' together with said sinking fund derived from
measures. The District may remove erosion , special assessments shall be sufficient to meet
control measures-if the District determines that : payment of the interest and principal of said
such measures interfere with the installation, ' bonds as the same become due;said tax shall
repair or maintenance of the District's mains. be known as the Sanitary'and Improvement
The Applicant shall repair or replace erosion ' District Tax and shall be payable annually in
control measures after the District has money.
completed the part of the main installation ' If a petition opposing this Resolution,signed
that required damage to or removal of the by property owners representing a majority of
erosion control measures. The-District shall 1, the front footage which may become subject to
not be responsible for damage to or removal { assessment for the cost of the improvements
of erosion control measures and shall not be i as set forth herein,is filed with the Clerk of the
responsible:to:.repair or replace them. The District within three(3)days before the date of
Applicant shall indemnify the.District from all the hearing on this Resolution,this Resolution
liabilities,federal,state,local or personal,:that shall not be passed.
may arise due to such damage or removal. The outer boundaries of the area which
This main installation is subject to the may become subject to special assessments
approval of the District's Board of Directors.If , for said improvements are proposed to be
the installation is not approved,this Agreement tt the same as the outer boundaries of Sanitary
is void.If the Applicant cancels this Agreement I and Improvement District No.603 of Douglas
or fails to perform under it,the Applicant shall County,Nebraska.
pay the District's design..costs and all other Said agreement has been reviewed by Lamp
costs and-expenses incurred. Rynearson&Associates,Inc.,engineers for the
Applicant shall not landscape or.allow District and-said engineers have filed with the
anyone else to landscape In the street right- Clerk of the District prior to the first publication
of-way or, in easements obtained for main ! of this Resolution,an estimate of the total costs
installation prior to the main installation. If of said-improvements, including engineering
Applicant does so,the District may remove any fees,legal fees,fiscal fees,Interest and other
landscaping necessary for installation of the miscellaneouscosts, which estimate is in the
water mains.Applicant shall pay the additional sum of$1,650,000.00.
costs of main installation caused by such To pay the cost of said improvement the
landscaping. Landscaping is defined as the Board of Trustees shall have the power to
placing of any decorative materials, Including '.. issue negotiable bonds of the District after
but not limited to, the planting:of trees or such-improvements have been completed and
shrubbery and the placing of-large rocks or accepted; said bonds to be called "Sanitary
other large decorative objects. and Improvement District Bonds"and shall be
This Agreement is conditioned upon receipt payable and bear interest as provided by the
of ail permits and easements necessary for the Statutes of the State of Nebraska.
main installation.
VIA EMAIL
May 26,2022
Chairman and Board of Trustees
Sanitary and improvement District No.615
of Douglas County,Nebraska
c/o Mr.Larry Jobeun,Attorney
Fullenkamp Jobeun Johnson&Beller,LLP
11440 West Center Road,Suite C
Omaha,Nebraska 68144
REFERENCE: S.I.D.No.615(Sanctuary Ridge)
Water Main Installation Agreement
Job No.0115119.11-067
Dear Members of the Board:
This is to advise you we have reviewed the enclosed service agreement for Metropolitan Utilities District(MUD)water
main installation as required to serve the current phase of Sanctuary Ridge(Lots 1-97),S.I.D. No. 615 of Douglas
County.We find the cost to be a reasonable and necessary expense of the District,per the Subdivision Agreement.
The following is our estimate of the total cost,which the District may be expected to incur for the cost:
Amount to be advanced to MUD for Water Main Installation: $976,554.00
Amount to be advanced to MUD for Pioneer Main Contribution: $228,727.00
Estimate Engineering,Miscellaneous,
Legal,Publication,Financing and Interest Cost: $436,369.00
TOTAL ESTIMATED PROJECT COST: $1,641,650.00
If the document meets with your approval,please properly execute and return them with payment of 81.205.281.00
directly to MUD.Please call if you have any questions.
Sincerely,
LAMP RYNEARSON,INC.
Caleb M.Snyder,P.E.
Project Manager
Enclosures
c: Dave Lanoha
kmp1L:\Engineering\0115119 SID Project Lenoha\DOCUMENTS\MUD\LTR Jobeun MUD Fee 220525.docx
Engineers Estimate No.6
Sanitary and Storm Sewer,Section 1 and Section 2
S.I.D.No.615(Sanctuary Ridge)
Job No.0115119.11-330/340
June 14,2022
Page 6
Chairman and Board of Trustees
Sanitary and Improvement District No. 615
of Douglas County,Nebraska
c/o Mr. Larry A.Jobeun,Attorney
Fullenkamp,Jobeun,Johnson&Beller LLP
11440 West Center Road,Suite C
Omaha,NE 68144
Dear Members of the Board:
This is an estimate of the work completed during the previous month on the above-referenced project.
It is recommended that payment be remitted to TAB CONSTRUCTION CO., in the amount shown due in accordance with our
records.
Sincerely,
LAMP RYNEARSON
rL
Bfyan D. Kratky,P.E.,E V SP
Senior Construction Engineer
c: Dave Lanoha
kls\L:\Engineering\0115119 SID Project Lanoha\ADMIN\SAN STM 1&2\EST 06 220614.docx
LAMP
RYNEARSON
14710 W.Dodge Rd.,Ste. 100
ESTIMATE NO: 6 Omaha,NE 68154
(P1402.496.2498
DATE: JUNE 14,2022 [F]402.496.2730
LampRynearson.com
CONTRACT FOR: SANITARY AND STORM SEWER,SECTION 1 AND SECTION 2
S.I.D. NO.615(SANCTUARY RIDGE)
LRA JOB NO: 0115119.11-330/340
OWNER: SANITARY IMPROVEMENT DISTRICT NO.615 OF DOUGLAS COUNTY,NEBRASKA
CONTRACTOR: TAB CONSTRUCTION CO.,4153 S.67TH AVENUE,OMAHA,NE 68117
TERMS: 90%MONTHLY,REMAINDER UPON FINAL ACCEPTANCE
TOTAL CONTRACT AMOUNT: $2,134,573.45
AMOUNT PAID ON PREVIOUS ESTIMATES: $1,184,961.08
ITEM APPROXIMATE
NO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT
:SE_CTION 1 (]QT$1=76i i := m
ANIT7[ rsEWER
' � �NTEHID�i _
v _ S-
+' 's _. _ r ._-c: .. m...» ,3.. .. .. ._. � .xa-�. __... mom..„ ..
1 CLEARING AND GRUBBING GENERAL 1 LS _ $60,574.00 $60,574.00
2 DELETE 0 LF $38.30 $0.00
3 DELETE 0 LF $42.35 80.00
4 CONSTRUCT 6"PIPE BEDDING 2,395 LF $6.70 $16,046.50
5 CONSTRUCT 8"PIPE BEDDING 6,718 LF $7.40 $49,713.20
6 CONSTRUCT 54"I.D.SANITARY MANHOLE(41 EA) 519.07 VF $577.30 $299,659.11
7 CONSTRUCT 8"MANHOLE DROP STRUCTURE 12.59 VF $322.30 $4,057.76
8 CONSTRUCT TAP TO EXISTING MANHOLE 0 EA $1,125.70 $0.00
9 CONSTRUCT 6"MANHOLE STUBOUT 38 EA $55.55 $2,110.90
10 CONSTRUCT 8"X 6"WYE 38 EA $170.20 $6,467.60
11 CONSTRUCT MANHOLE RING COLLAR 12 EA $716.10 $8,593.20
12 CONSTRUCT EXTERNAL FRAME SEAL 12 EA $385.90 $4,630.80
13 CONSTRUCT TRENCH PLUG 1 EA $1,771.50 $1,771.50
14 STABILIZE TRENCH W/FOUNDATION ROCK 352 TN $30.50 $10,736.00
15 STABILIZE TRENCH W/TYPE"A"RIP RAP 0 TN $55.55 $0.00
16 FURNISH AND INSTALL GEOTEXTILE FABRIC 0 SY $1.10 $0.00
17 FURNISH AND INSTALL GEOGRID 0 SY $1.60 $0.00
18 EXCAVATION FOR EXTRA DEEP SANITARY SEWER 355 VF-LF $10.60 $3,763.00
19 PERFORM CCTV PIPELINE INSPECTION 6,725 LF $4.25 $28,581.25
Leading a L ac
Engineers Estimate No.6
Sanitary and Storm Sewer,Section 1 and Section 2
S.I.D.No.615(Sanctuary Ridge)
Job No.0115119.11-330/340
June 14,2022
Page 2
ITEM APPROXIMATE
NO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT
CHANGE ORDER#1
19A CONSTRUCT 6"SANITARY SEWER PIPE 2,395 LF $41.26 $98,817.70
19B CONSTRUCT 8"SANITARY SEWER PIPE 6,718 LF $44.28 $297,473.04
SUBTOTAL SANITARY-INTERIOR $892,995.56
- -=$ LTARI FO- R om. bat- 15 ---- - -. =1 s . . . `„ _ _ .'
20 CLEARING AND GRUBBING GENERAL 1 LS $12,000.00 $12,000.00
21 EXPLORATORY EXCAVATION 9 HR $280.10 $2,520.90
BORE AND JACK 8"STEEL CASING W/4"SANITARY SEWER
22 PIPE 130 LF $222.90 $28,977.00
23 DELETED 0 LF $16.20 $0.00
24 CONSTRUCT LIFT STATION 0.5 EA $275,475.00 $137,737.50
25 TAP EXISTING LIFT STATION 1 EA $2,804.10 $2,804.10
26 CONSTRUCT SILT FENCE 0 LF 82.90 $0.00
27 CLEANOUT SILT FENCE 0 LF $1.10 80.00
28 REMOVE SILT FENCE 1,604 LF $1.10 $1,764.40
29 SEEDING-TYPE"TEMPORARY SEED MIX" 0 AC $322.40 $0.00
30 STRAW MULCH 0 AC $540.90 $0.00
31 SEEDING-TYPE"A" 0 AC $2,458.70 $0.00
32 ROLLED EROSION CONTROL,TYPE II 0 SY $1.75 $0.00
33 LANDSCAPING RESTORATION ALLOWANCE 0 LS $15,000.00 $0.00
34 IRRIGATION SYSTEM MODIFICATION ALLOWANCE 0.21 LS $8,000.00 $1,680.00
35 DEWATERING-LIFT STATION 0 LS $3,113.00 $0.00
36 CONSTRUCT 6"AGGREGATE BASE COURSE 0 SY $21.90 $0.00
CHANGE ORDER#1
36A CONSTRUCT 4"FORCE MAIN WITH TRACER WIRE 1,257 LE $16.87 $21,205.59
SUBTOTAL SANITARY FORCE MAIN OUTFALL $208,689.49
SUBTOTAL SANITARY SEWER AND SANITARY FORCE MAIN OUTFALL $1,101,685.05
e SI i3m7sE,Aftut Si.i ',1":: '`.-. - ,:ft.-J '« A
37 GENERAL GRADING AND SHAPING 0 LS $26,481.00 $0.00
38 CONSTRUCT 15"PIPE BEDDING 152 LF $9.15 $1,390.80
39 CONSTRUCT 18"PIPE BEDDING 1,058 LF $9.50 $10,051.00
40 CONSTRUCT 24"PIPE BEDDING 654 LF $9.85 $5,441.90
41 CONSTRUCT 30"PIPE BEDDING 69 LF $14.15 $976.35
42 CONSTRUCT 36"PIPE BEDDING 578 LF $28.25 $16,328.50
43 CONSTRUCT 15"R.C.P.,CLASS III 152 LF $43.30 $6,581.60
44 CONSTRUCT 18"R.C.P.,CLASS III 1,058 LF $44.75 $47,345.50
Engineers Estimate No.6
Sanitary and Storm Sewer,Section 1 and Section 2
S.I.D.No.615(Sanctuary Ridge)
Job No.0115119.11-330/340
June 14,2022
Page 3
ITEM APPROXIMATE
NO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT
45 CONSTRUCT 24"R.C.P.,CLASS III 654 LF $60.10 $39,305.40
46 CONSTRUCT 30"R.C.P.,CLASS III 69 LF $87.80 $6,058.20
47 CONSTRUCT 36"R.C.P.,D(0.01)=1,350 578 LF $98.60 $56,990.80
48 REMOVE 36"C.S.P. PIPE 150 LF $26.15 $3,922.50
49 CONSTRUCT 54"I.D.FLATTOP MANHOLE(11 EA) 75.6 VF $727.80 $55,021.68
50 CONSTRUCT 72"I.D. FLATTOP MANHOLE(2 EA) 35.75 VF $875.20 $31,288.40
51 CONSTRUCT MANHOLE RING COLLAR 8 EA $710.00 $5,680.00
52 CONSTRUCT EXTERNAL FRAME SEAL 8 EA $385.90 $3,087.20
53 CONSTRUCT 36"R.C. FLARED END SECTION 5 EA $2,158.40 $10,792.00
54 STABILIZE TRENCH W/CRUSHED LIMESTONE 263 TN $30.15 $7,929.45
55 CONSTRUCT ENERGY DISSIPATION(RIP RAP APRON) 150 TN $89.15 $13,372.50
56 CONSTRUCT SHEET WALLS 240 SF $35.20 $8,448.00
57 CONSTRUCT SILT FENCE 1,311 LF $2.90 $3,801.90
58 CLEANOUT SILT FENCE 0 LF $1.10 $0.00
59 CLEANOUT SILT BASIN 0 CY $4.35 $0.00
60 SEEDING-TYPE"TEMPORARY SEED MIX" 0 AC $322.40 $0.00
61 HAY OR STRAW MULCH 0 AC $540.90 $0.00
CONSTRUCT ROCK RIP-RAP-TYPE"A"FOR TRENCH
62 STABILIZATION 169 TN $55.55 $9,387.95
63 FURNISH AND INSTALL GEOGRID 1,000 SY $1.60 $1,600.00
64 FURNISH AND INSTALL GEOTEXTILE FABRIC 1,000 SY $1.10 $1,100.00
65 PERFORM CCTV PIPELINE INSPECTION 493 LF $3.05 $1,503.65
SUBTOTAL STORM SEWER $348,405.28
TOTAL SECTION 1 -SANITARY SEWER AND STORM SEWER $1,450,090.33
a, /SECTIO. I O X$0' T --* ---r J - �... . .. P ca
' -e
S‘ SIAPANtAnttltEkilil4i:77.--JIIM4i:
1 CLEARING AND GRUBBING GENERAL 1 LS $10,595.00 $10,595.00
2 EXPLORATORY EXCAVATION 0 HR $280.10 $0.00
3 DELETE 0 LF $39.10 $0.00
4 DELETE 0 LF $42.85 $0.00
5 CONSTRUCT 6"PIPE BEDDING 618.5 LF $6.70 $4,143.95
6 CONSTRUCT 8"PIPE BEDDING 1,193 LF $7.40 $8,828.20
7 CONSTRUCT 54"I.D.SANITARY MANHOLE(7 EA) 100.79 VF $564.10 $56,855.64
8 CONSTRUCT 6"MANHOLE STUBOUT 8 EA $55.55 $444.40
9 CONSTRUCT 8"X 6"WYE 13 EA $170.20 $2,212.60
10 CONSTRUCT MANHOLE RING COLLAR 1 EA $905.40 $905.40
Engineers Estimate No.6
Sanitary and Storm Sewer,Section 1 and Section 2
S.I.D.No.615(Sanctuary Ridge)
Job No.0115119.11-330/340
June 14,2022
Page 4
ITEM APPROXIMATE
NO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT
11 CONSTRUCT EXTERNAL FRAME SEAL 1 EA $385.90 $385.90
12 TAP EXISTING SANITARY MANHOLE 1 EA $1,125.70 $1,125.70
13 STABILIZE TRENCH W/FOUNDATION ROCK 0 TN $30.15 $0.00
14 PERFORM CCTV PIPELINE INSPECTION 1,200 LF $4.25 $5,100.00
15 REMOVE PAVEMENT 16 SY $21.30 $340.80
16 CONSTRUCT 8"ASPHALT PAVEMENT 10.56 TN $218.50 $2,307.36
17 SAW CUT PAVEMENT-FULL DEPTH 84 LF $10.50 $882.00
18 PAVEMENT MARKINGS 0 LF $26.50 $0.00
19 TEMPORARY TRAFFIC CONTROL 1 LS $2,247.80 $2,247.80
CHANGE ORDER#1
19A CONSTRUCT 6"SANITARY SEWER PIPE 618.5 LF $42.06 $26,014.11
19B CONSTRUCT 8"SANITARY SEWER PIPE 1,193 LF $44.78 $53,422.54
CHANGE ORDER#2
REMOVE AND REPLACE SANITARY SEWER AND
19C APPURTENANCES 1 LS $44,329.90 $44,329.90
SUBTOTAL SANITARY SEWER $220,141.30
'; , r STORM4$EVYER r . ' -L :: _._ i
20 GENERAL GRADING AND SHAPING 0 LS $6,295.00 $0.00
21 CONSTRUCT 18"PIPE BEDDING 353 LF $9.50 $3,353.50
22 CONSTRUCT 24"PIPE BEDDING 114 LF $9.85 $1,122.90
23 CONSTRUCT 30"PIPE BEDDING 36 LF $14.15 $509.40
24 CONSTRUCT 18"R.C.P.,CLASS III 353 LF $44.35 $15,655.55
25 CONSTRUCT 24"R.C.P.,CLASS III 114 LF $61.95 $7,062.30
26 CONSTRUCT 30"R.C.P.,CLASS III 36 LF $90.35 $3,252.60
27 CONSTRUCT 24"R.C. FLARED END SECTION 3 EA $1,408.80 $4,226.40
28 CONSTRUCT 30"R.C. FLARED END SECTION 2 EA $1,732.20 $3,464.40
29 STABILIZE TRENCH W/CRUSHED LIMESTONE 0 TN $30.15 $0.00
30 CONSTRUCT POND OUTLET STRUCTURE 1 EA $5,461.60 $5,461.60
31 CONSTRUCT ROCK RIP-RAP-TYPE"B" 0 TN $92.35 $0.00
32 CONSTRUCT ANTI-SEEP COLLAR 2 EA $507.90 $1,015.80
33 CONSTRUCT SILT FENCE 0 LF $2.90 $0.00
34 CLEANOUT SILT FENCE 0 LF $1.10 $0.00
35 CLEANOUT SILT BASIN 0 CY $4.35 $0.00
36 SEEDING-TYPE"TEMPORARY SEED MIX" 0 AC $322.40 $0.00
37 HAY OR STRAW MULCH 0 AC $540.90 $0.00
Engineers Estimate No.6
Sanitary and Storm Sewer,Section 1 and Section 2
S.I.D.No.615(Sanctuary Ridge)
Job No.0115119.11-330/340
June 14,2022
Page 5
ITEM APPROXIMATE
NO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT
CONSTRUCT ROCK RIP-RAP-TYPE"A"FOR TRENCH
38 STABILIZATION 0 TN $55.55 $0.00
39 FURNISH AND INSTALL GEOGRID 0 SY $1.85 $0.00
40 FURNISH AND INSTALL GEOTEXTILE FABRIC 0 SY $1.25 $0.00
41 CCTV PIPELINE INSPECTION 0 LF $3.05 $0.00
42 REMOVE 15"STORM SEWER PIPE 25 LF $24.05 $601.25
43 REMOVE 24"STORM SEWER PIPE 25 LF $24.05 $601.25
44 REMOVE AND REPLACE DRIVEWAY PAVEMENT 14 SY
$100.80 $1,411.20
SUBTOTAL STORM SEWER $47,738.15
TOTAL SECTION 2-SANITARY SEWER AND STORM SEWER $267,879.45
TOTAL SECTIONS 1 AND SECTION 2 $1,717,969.78
OWNER'S RETAINAGE(10%) $171,796.98
LESS AMOUNT PREVIOUSLY PAID $1,184,961.08
AMOUNT DUE CONTRACTOR $361,211.72
Engineers Estimate No. 1
Paving,Section 1
S.I.D.No.615(Sanctuary Ridge)
Job No.0115119.11-350
July 7,2022
Page 4
VIA Email
Chairman and Board of Trustees
Sanitary and Improvement District No.615
of Douglas County,Nebraska
c/o Mr. Larry A.Jobeun,Attorney
Fullenkamp,Jobeun,Johnson&Beller LLP
11440 West Center Road,Suite C •
Omaha, NE 68144
Dear Members of the Board:
This is an estimate of the work completed during the previous month on the above-referenced project.
It is recommended payment be remitted to MBC CONSTRUCTION LLC.,in the amount shown due in accordance with our records.
Sincerely,
LAMP RYNEA SON
Bryy . Kratky,P.E.,ENV SP
Senior Construction Engineer
c: Dave Lanoha
kmp\L:\Engineering\0115119 SID Project Lanoha\ADMIN\PAV 1\EST 01 220707.dacx
LAMP
RYNEARSON
ESTIMATE NO: 1 14710 W.Dodge Rd.,Ste. 100
Omaha,NE 68154
DATE: JULY 7,2022 [P]402.496.2498
IF]402.496.2730
CONTRACT FOR: PAVING,SECTION 1 LampRynearson.com
S.I.D.NO.615(SANCTUARY RIDGE)
LRA JOB NO: 0115119.11-350
OWNER: SANITARY IMPROVEMENT DISTRICT NO.615 OF DOUGLAS COUNTY,NEBRASKA
CONTRACTOR: MBC CONSTRUCTION LLC.,6002 N.89TH CIRCLE,OMAHA,NE 68134
TERMS: 90%MONTHLY,REMAINDER UPON FINAL ACCEPTANCE
TOTAL CONTRACT AMOUNT: $1,795,350.55
AMOUNT PAID ON PREVIOUS ESTIMATES: $0.00
ITEM APPROXIMATE UNIT
NO. DESCRIPTION QUANTITY PRICE AMOUNT
SECTION 1 (LOTS 1-76)
PAVING-INTERIOR
1 7"CONCRETE PAVEMENT-TYPE L65 10,686 SY $49.40 $527,888.40
2 COMMON EARTH EXCAVATION 6,417 CY $4.60 $29,518.20
3 5"PC CONCRETE SIDEWALK-TYPE L6 0 SF $6.32 $0.00
4 CONSTRUCT 1"EXPANSION JOINT 300 LF $5.59 $1,677.00
5 CONSTRUCT 7"PCC PAVEMENT WITH INTEGRAL 4"SPEED HUMP 0 EA $11,760.00 $0.00
6 ADJUST MANHOLE TO GRADE(24 SS,3 STM) 21 EA $243.00 $5,103.00
7 CONSTRUCT EXTERNAL FRAME SEAL 21 EA $586.00 $12,306.00
8 CONSTRUCT CURB INLET 2 EA $4,671.00 $9,342.00
9 SEEDING-TYPE"TEMPORARY SEED MIX" 0 AC $328.00 $0.00
10 INSTALL MULCH 0 AC $550.00 $0.00
11 JET EXISTING SEWER 0 LF $0.78 $0.00
12 CONSTRUCT SILT FENCE 0 LF $2.93 $0.00
13 CLEANOUT SILT FENCE 0 LF $1.11 $0.00
14 CLEANOUT SILT BASIN 0 CY $4.44 $0.00
15 CURB INLET PROTECTION 0 EA $250.00 $0.00
16 TOPSOIL ISLAND 0 CY $42.95 $0.00
17 CONSTRUCT MEDIAN SURFACING 0 SF $9.25 $0.00
18 CONSTRUCT MEDIAN NOSE 0 EA $463.00 $0.00
19 CONSTRUCT THICKENED EDGE 0 LF $9.42 $0.00
20 CONSTRUCT PREFORMED LEFT ARROW PAVEMENT STRIPING 0 EA $722.00 $0.00
21 CONSTRUCT PREFORMED 4"WIDE WHITE PAVEMENT STRIPING 0 LF $5.89 $0.00
SUBTOTAL PAVING SECTION 1 (LOTS 1-76) $585,834.60
Leaving a
Engineers Estimate No. 1
Paving,Section 1
S.I.D.No.615(Sanctuary Ridge)
Job No.0115119.11-350
July 7,2022
Page 2
ITEM APPROXIMATE UNIT
NO. DESCRIPTION QUANTITY PRICE AMOUNT
SECTION 2(LOTS 77-97)
PAVING-INTERIOR
1 7"CONCRETE PAVEMENT-TYPE L65 3,811 SY $49.35 $188,072.85
2 5"PC CONCRETE SIDEWALK-TYPE L6 0 SF $6.43 $0.00
3 CONSTRUCT 7"PCC PAVEMENT WITH INTEGRAL 4"SPEED HUMP 0 EA $11,812.00 $0.00
4 REMOVE PAVEMENT 260 SY $12.10 $3,146.00
5 SAW-CUT PAVEMENT FULL DEPTH 100 LF $4.99 $499.00
6 EARTHWORK EXCAVATION 900 CY $13.15 $11,835.00
7 COMMON EARTH EXCAVATION 1,550 CY $4.60 $7,130.00
8 CONSTRUCT END OF STREET BARRICADE 0 EA $1,084.00 $0.00
9 CONSTRUCT 6"PCC TEMPORARY TURNAROUND 0 SY $65.40 $0.00
10 ADJUST MANHOLE TO GRADE(5 SAN) 5 EA $243.00 $1,215.00
11 CONSTRUCT EXTERNAL FRAME SEAL 5 EA $586.00 $2,930.00
12 CONSTRUCT CURB INLET 4 EA $4,671.00 $18,684.00
13 SEEDING-TYPE"TEMPORARY SEED MIX" 0 AC $328.00 $0.00
14 INSTALL MULCH 0 AC $550.00 $0.00
15 JET EXISTING SEWER 0 LF $0.78 $0.00
16 CONSTRUCT SILT FENCE 0 LF $2.93 $0.00
17 CLEANOUT SILT FENCE 0 LF $1.11 $0.00
18 CLEANOUT SILT BASIN 0 CY $4.44 $0.00
19 CURB INLET PROTECTION 0 EA $250.00 $0.00
20 CONSTRUCT MEDIAN SURFACING 0 SF $9.43 $0.00
21 CONSTRUCT MEDIAN NOSE 0 EA $463.00 $0.00
22 CONSTRUCT THICKENED EDGE 46 LF $9.42 $433.32
23 CONSTRUCT PREFORMED LEFT ARROW PAVEMENT STRIPING 0 EA $722.00 $0.00
24 CONSTRUCT PREFORMED 4"WIDE WHITE PAVEMENT STRIPING 0 LF $5.89 $0.00
25 MAINTAIN HOMEOWNER ACCESS OFF SKYLINE DRIVE 1 LS $3,078.00 $3,078.00
SUBTOTAL PAVING SECTION 2(LOTS 77-97) $237,023.17
ARTERIAL PAVING-US 275/W CENTER RD
1 GENERAL CLEARING AND GRUBBING 0 LS $84,237.00 $0.00
2 REMOVE PAVEMENT 0 SY $12.10 $0.00
3 SAWING PAVEMENT 0 LF $7.20 $0.00
4 REMOVE CULVERT PIPE 0 LF $46.40 $0.00
5 PAVEMENT MARKING REMOVAL 0 LF $1.50 $0.00
6 REMOVE AND RESET MAILBOX 0 EA $514.00 $0.00
7 REMOVE SIGN 0 EA $367.00 $0.00
8 EARTHWORK MEASURED IN EMBANKMENT 0 CY $13.15 $0.00
Engineers Estimate No.1
Paving,Section 1
S.I.D.No.615(Sanctuary Ridge)
Job No.0115119.11-350
July 7,2022
Page 3
ITEM APPROXIMATE UNIT
NO. DESCRIPTION QUANTITY PRICE AMOUNT
9 9"CONCRETE PAVEMENT,CLASS 47B-3500 0 SY $74.65 $0.00
10 10"ASPHALTIC CONCRETE,TYPE SPR 0 TON $152.00 $0.00
11 4"ASPHALTIC CONCRETE,TYPE SPR(FINE) 0 TON $154.00 $0.00
12 4"AGGREGATE FOUNDATION COURSE 0 SY $1.00 $0.00
13 SUBGRADE PREPARATION 0 SY $1.00 $0.00
14 24"CULVERT PIPE,TYPE 2 0 LF $82.75 $0.00
15 24"CONCRETE FLARED-END SECTION 0 EA $1,706.00 $0.00
16 ROCK RIPRAP,TYPE A 0 TN $96.90 $0.00
17 EROSION CONTROL,CLASS 1D 0 SY $1.78 $0.00
18 SILT CHECK,TYPE 2-HIGH 0 LF $6.39 $0.00
5"WHITE WET REFLECTIVE PAVEMENT MARKING,TYPE 4
19 GROOVED 0 LF $6.55 $0.00
5"YELLOW WET REFLECTIVE PAVEMENT MARKING,TYPE 4
20 GROOVED 0 LF $6.55 $0.00
12"YELLOW WET REFLECTIVE PAVEMENT MARKING,TYPE 4
21 GROOVED 0 LF $14.15 $0.00
22 TEMPORARY TRAFFIC CONTROL 0 LS $2,194.00 $0.00
SUBTOTAL ARTERIAL PAVING $0.00
TOTAL ESTIMATE WORK COMPLETED $822,857.77
OWNER'S RETAINAGE(10%) $82,285.78
LESS AMOUNT PREVIOUSLY PAID $0.00
AMOUNT DUE CONTRACTOR $740,571.99 i
N FULLENKAMP John H.Fullenkamp
Fin JOBEUN Larry A.Jobeun
Mark B.Johnson
® B JOHNSON St Brent W.Beller
BELLER LLP Robert T.Griffith
Writers e-mail:larrv@fiblaw.com
Writers direct dial:(402)691-5265
July 7, 2022
Chairman and Board of Trustees
Sanitary and Improvement District
No. 615 of Douglas County, Nebraska
Statement of Services Rendered
For Legal Services rendered in connection with the payment to:
a. TAB Construction Co.for completion of a portion of the Sanitary $361,211.72
and Storm Sewer—Section 1 &2 Improvements and in accordance
with Pay Est. No. 6.
b. MBC Construction, LLC for completion of a portion of the Paving $740,571.99
Section I improvements in accordance with Pay Est. No. 1.
c. Metropolitan Utilities District for construction of the water main $1,205,281.00
extension and related appurtenances and payment of pioneer main
fees pursuant to the above-approved Water Main Ext.Agreement.
LEGAL FEES(5%): $55,089.19
LEGAL FEES(2%): $24,105.62
EXPENSES: $ -0-
Filing Fees, Publications, Copying,
& Postage
TOTAL AMOUNT DUE: $79,194.81
/s/Larry A. Jobeun
Attorney for the District
11440 W. Center Road, Ste. C—Omaha,Nebraska, 68144—Phone: (402)334-0700—Website:www.fiblaw.com
AGENDA
Sanitary and Improvement District No. 615 of Douglas County, Nebraska ("Sanctuary Ridge");
Meeting to be held July 7, 2022, at 4:30 p.m. at 17070 Wright Plaza, Ste. 200, Omaha,Nebraska.
1. Present Nebraska Open Meetings Act; Trustee roll call.
• David Lanoha—Chair
• Jason Lanoha
• Chris Lanoha
• Cassie Preister—Clerk
• {Vacant}
2. Vote on and approve Resolution of Necessity recommending that the District enter into a
Water Main Extension Agreement with Metropolitan Utilities District, for and in
consideration of the construction of the water distribution system for the District and any
related appurtenances, and the payment of any costs related thereto, the same having been
presented and approved, in form, at the June 9, 2022 meeting (published June 22 and 29,
2022 in the Daily Record).
3. Present statements,vote on and approve payment from the Construction Fund Account of the
District for the following:
a. TAB Construction Co. for completion of a portion of the Sanitary $361,211.72
and Storm Sewer—Section 1 & 2 Improvements and in accordance
with Pay Est. No. 6.
b. MBC Construction, LLC for completion of a portion of the Paving $740,571.99
Section I improvements in accordance with Pay Est. No. 1.
c. Metropolitan Utilities District for construction of the water main $1,205,281.00
extension and related appurtenances and payment of pioneer main
fees pursuant to the above-approved Water Main Ext. Agreement.
d. Fullenkamp Jobeun Johnson& Beller, LLP for legal services ren- $79,194.81
dered in connection with items a.),b.) 5%and c.) (2%) hereinabove.
e. D.A. Davidson& Co. for underwriting services relating to Construc- $47,725.19
tion Fund Warrants issued at this meeting (2%).
4. Any and all business before the Board as deemed necessary; meeting adjourned.