The attached resolution approves the contract with McKinnis Roofing and Sheet Metal for OPW
52545-SP, being re-roof of Fire Station 1463, located at 16736 "S" Street.
The following bids were received on February 26, 2014. A detailed bid tabulation is attached.
Contractor Total Bid
McKINNIS ROOFING AND SHEET METAL $68,550.00 (LOW BID)
Stonebrook Roofing, Inc. $72,898.85
R L Craft Co. of Omaha $89,877.00
Scott Enterprises, Inc. $94,227.00
The contractor has a current Contract Compliance Report Form (CC-1) on file. As is City
policy, the Human Rights and Relations Department will review the contractor to ensure
compliance with the Contract Compliance Ordinance.
The Finance Department is authorized to pay the cost of OPW 52545-SP from the Contingent
Liability Fund 11114, General Government Organization 132022, year 2014 expenditures.
The Public Works Department recommends the acceptance of the bid from McKinnis Roofing
and Sheet Metal, being the lowest and best bid received, and requests your consideration and
approval of this resolution.
Respectfully submitted, Referred to City Council for Consideration:
C*-2- 0--ftil g Robert G. Stubbe, P.E. Date Mayor's Office Date
Public Works Director
Approved as to Funding: Approved:
A,746 q/o ' -6(,"-• iCIC4 (
Finance DirectorStephen B. s Date Human Department
and Relations Date
243514scp
BID TABULATION City of Omaha Public Works Department
Project No. OPW 52545(Rebid)
McKinnis Roofing& Stonebrook R.L. Craft Scott Enterprises,
:Fire Station#63 Re-Roof Sheet Metal Roofing Company Inc.
Fund/orgn 11114/132022
Advertised February 5,2014
Bid Date February 26, 2014 ENGINEER'S
ESTIMATE LOW BID
LUMP SUM BID $29,853.32 $68,550.00 $72,898.85 $89,877.00 $94,227.00
Certified by:
/(� Date: 02 li`F
gg P:\Gerhard\Projects\Bid Tab-Lump Sum Bid.doc 02/26/14 page 1
C-25A CITY OF OMAHA
LEGISLATIVE CHAMBER
Omaha,Nebraska
RESOLVED BY THE CITY COUNCIL OF THE CITY OF OMAHA:
WHEREAS, bids were submitted on February 26, 2014 for OPW 52545-SP, being re-
roof of Fire Station #63, located at 16736 "S" Street; and,
r
WHEREAS, McKinnis Roofing and Sheet Metal submitted a bid of $68,550.00, being
the lowest and best bid received for OPW 52545-SP.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF OMAHA:
THAT, as recommended by the Mayor, the contract with McKinnis Roofing and Sheet
Metal for OPW 52545-SP, being re-roof of Fire Station #63, located at 16736 "S" Street in the
amount of$68,550.00 is hereby approved; and, that the Finance Department is authorized to pay
this cost from the Contingent Liability Fund 11114, General Government Organization 132022,
year 2014 expenditures.
243614scp APPROVED AS TO FORM:
G 57 4' ,a
C `�ITY ATTORNEY DATE
By /14, 11‘4.
Councilmember
Adopted MAY 1 3 2014 9-e
"i#j''I -',r__—i--- ity Clerk J /J#
Approv
Mayor
NO. i -2
Resolution by
Res. that, as recommended by the Mayor, the
contract with McKinnis Roofing and Sheet
Metal for OPW 52545-SP, being re-roof of
Fire Station #63, located at 16736 "S" Street
in the amount of $68,550.00 is hereby
approved; and, that the Finance Department is
authorized to pay this cost from the
Contingent Liability Fund 11114, General
Government Organization 132022, year 2014
expenditures.
243614Ascp
Presented to City Council
MAY t32014
Adopted
gutter grown